Back to blogProjects

Leduc County Tower: 5th Floor Renovations

How careful planning, daily communication and considerate site logistics transformed an occupied office in Nisku.

By John Smigelski

Completed office renovation at Leduc County Tower

The County of Leduc engaged ProQual to renovate a wing on the fifth floor of one of its buildings in Nisku. The work began with demolition and continued through a complete tenant improvement, while the rest of the building remained in use.

Project at a glance

Client
Leduc County
Location
Nisku, Alberta
Work
Demolition and tenant improvements to a fifth-floor office wing
Site condition
The rest of the building remained in use
Coordination
Trade work, elevator access, material movements and separation from occupied areas

These details come from ProQual’s published project account. The article date is not a claimed construction completion date.

Explore commercial renovations and tenant improvements

From an existing office to a new workspace

The initial scope included removing most of the existing walls, carpets, ceiling tiles and insulation, along with some electrical components and furniture. The fit-out then brought together new studs, drywall, paint, electrical, millwork, plumbing, carpet, ceiling tiles, insulation and partitions with windows.

The client arrived with a vision for the layout and materials. ProQual worked through the options with them, explaining what was practical and which materials would best support the finished space.

Working around a busy building

Renovating an occupied property means thinking beyond the work area. ProQual coordinated elevator use and material movements with building management to avoid the busiest arrival and departure periods.

Doors separating the construction area from the occupied floor stayed closed to reduce disruption. The team cleaned as work progressed so dust and debris were not carried through the elevators and common areas.

Planning the logistics

One elevator was a foot taller than the other. That difference mattered when moving steel studs, drywall and large furniture. The team arranged access to the taller elevator and used the stairs for the longest pieces that still could not fit.

High winds in Nisku also affected waste handling. Materials were secured during transport, and the dumpster was packed with lighter waste below heavier material to reduce the risk of debris blowing across the parking lot.

Keeping the trades and client aligned

Carpet, electrical, mechanical and millwork trades were coordinated throughout the project. Daily updates and regular contact with the client's representative helped keep decisions clear and work aligned with expectations.

The completed office was delivered on schedule and on budget, according to ProQual's published project account. It is an example of how listening, coordination and practical planning can support a successful renovation in an active workplace.

Talk to ProQual

Practical advice, clear communication and accountable commercial work in Edmonton.